Construction schedule template
Plan a small home extension, from site prep to handoff.
Free template. No account needed.
How to use this template
- Download the CSV and open it in your spreadsheet app.
- Replace the sample dates with dates agreed with your contractor. Check that each task still starts after the work it depends on.
- To draw your own chart, copy the plan text, edit the task lines, and paste it into a Gantt app below.
End dates include the last scheduled day. Dependencies in the CSV are notes you can update as dates change.
Draw it in your tool
- Confluence & JiraGuideStore listing
- Adobe ExpressGuideStore listing
- FramerGuideStore listing
- BubbleGuideStore listing
FAQs
Where should I leave time for inspection?
Leave a gap between the inspection and any work that depends on it. In this example, there is a gap before the electrical and plumbing work starts.
How do I show a long-lead material order?
Give ordering and delivery their own schedule entry. Check the delivery date against the first task that needs the materials.
What should I put on the schedule if I’m renovating without an extension?
Swap the groundworks and shell phases for demolition and any structural work in your scope. Keep the finishes and handoff phases if they apply.