Make a readable Mermaid Gantt chart in Confluence or Jira
Write the plan as Mermaid Gantt text, paste it into a Mermaid diagram element on the page, and keep it readable with short task names, weekly axis labels and sections.
A Gantt chart that reads well, ready to paste
gantt
title Release plan
dateFormat YYYY-MM-DD
axisFormat %d %b
tickInterval 1week
excludes weekends
section Build
Design :done, a1, 2026-01-05, 7d
Development :active, a2, after a1, 14d
section Launch
Testing :crit, a3, after a2, 5d
Go live :milestone, after a3, 0dPaste it with or without the ```mermaid fences. The axisFormat and tickInterval lines are what keep the date labels from crowding together.
Readable-chart checklist
| Problem | Line to add or change |
|---|---|
| Dates on the axis overlap | axisFormat %d %b (or %b %Y for long plans) |
| Too many grid lines | tickInterval 1week or 1month |
| Weekends stretch the plan | excludes weekends |
| Bars too thin to read | Fewer tasks per section, shorter names, full-width page |
| Key work gets lost | Tag it crit; mark dates with milestone |
Text Diagrams, our Mermaid app for Confluence and Jira, is live on the Atlassian Marketplace. It has a Gantt template, zoom and Fit buttons, and SVG or PNG downloads.
Get it on Atlassian MarketplaceWhat each line means
| Line | What it does |
|---|---|
gantt | Starts a Gantt chart |
dateFormat YYYY-MM-DD | How dates are written in your text |
axisFormat %d %b | How dates show on the axis ("05 Jan") |
tickInterval 1week | One axis label per week |
excludes weekends | Skips Saturdays and Sundays when counting days |
section Build | Groups the tasks below it into a labelled band |
Design :done, a1, 2026-01-05, 7d | Task name, status tag, id, start date, length |
Development :active, a2, after a1, 14d | Starts when task a1 ends (status tags are optional) |
Go live :milestone, after a3, 0d | A diamond marking one moment |
Status tags go before the id: done, active, crit (critical) or milestone.
Why is a Mermaid Gantt chart too small in Confluence?
A Mermaid Gantt chart can become hard to read when long task names, crowded daily labels, many tasks in one section, or a narrow Confluence page squeeze the drawing. Shorten task names and use a full-width page. Set axisFormat to %d %b or %b %Y, then use tickInterval 1week or 1month for longer plans. Split tasks across sections. Once BrightDesk Text Diagrams is approved, it will add zoom out, Fit and zoom in buttons above each diagram, plus SVG and PNG downloads.
Can a Mermaid Gantt chart follow Jira issue dates?
A Mermaid Gantt chart cannot follow Jira issue dates, in BrightDesk Text Diagrams or any other Mermaid app. The chart uses the dates and task relationships you write in the diagram text. Changes to Jira issues do not update the drawing. Edit the text whenever the plan changes, then save the revised diagram. Placing a chart on an issue provides context, but does not connect the chart's schedule to issue fields.
When is a Mermaid Gantt chart suitable, and when is a planning app better?
A Mermaid Gantt chart suits a written plan that needs a clear picture of task order, duration, and milestones. Keep the text beside a proposal, project brief, or status note when readers need to understand the schedule. A planning app is better when people need to drag tasks to new dates, track resources, or manage a schedule through issue fields. Mermaid draws the plan you type and offers no drag-to-reschedule controls or resource tracking. Choose according to how the team will maintain the plan.
Every option is in the Mermaid Gantt documentation.
Last updated 14 November 2026.